Please note that the project schedule is subject to change.

  • Early 2015–Fall 2017: Project routing process was initiated. Xcel Energy coordinated with local jurisdictions, evaluated resources potentially impacted and considered route alternatives that would reduce or eliminate environmental impacts based on consideration of engineering feasibility.
  • Fall 2016: Project began permitting process.
  • Spring 2019: Project construction began. To see the latest construction information, visit our Tungsgten to Bobtail Natural Gas Project construction page.
  • 2019-2020: Project in-service date.